Home
Construction Law
Constructionary
Case Law Update
Contact Us
A
A
A
Visit MinterEllison
Home
Construction Law
Constructionary
Case Law Update
Contact Us
Chapters
1
How a legally binding contract is formed
Heads of agreement
Early works contract
Letter of intent
The effect of privity of contract
The effect of promissory estoppel
2
What are project delivery methods?
Construct only
Design and construct
Project and construction management
EPC and EPCM
Relationship models
Private Public Partnerships
Choosing project delivery methods
3
What is Tendering
Common types of tender processes
Usual steps in a tender process
Tender process contracts
Managing the main risks of tendering
4
What are variations?
Why have a variations power?
When is the variations power limited?
How do variations occur?
Time bars
Valuation of Variations
What to do when things go wrong
5
Who is the superintendent?
Appointment of a superintendent
Obligations of a superintendent
Role of a superintendent
Liability of a superintendent
6
What is the site?
Accessing the site
Repossession of the site
Neighbours and adjoining properties
Latent conditions
Managing the risk of latent conditions
7
Why security is given
Types of security
Calling on security
Releasing security
Legislation affecting security
8
What is the Building Code of Australia?
What does the BCA cover?
Fire safety and cladding
What is the performance-based Building Code?
How to satisfy the performance requirements
Deemed-to-satisfy solutions
Performance solutions
Assessment methods
9
Progress payments
Payment claims
Progress certificates
Final certificates
10
What is a defect?
Rectification prior to completion of works
Rectification after completion of works
Defects liability period
Quantum of damages
11
Time in construction contracts
Extension of time regimes
Extension of time procedures
The float
Assessing delay
12
What are liquidated damages?
Why use liquidated damages clauses?
The doctrine of penalties – when are liquidated damages unenforceable?
Completing the contract
13
Delay, disruption and prolongation
Delay costs and delay damages
Acceleration costs
14
Building Industry Regulation
NEW SOUTH WALES
QUEENSLAND
SOUTH AUSTRALIA
TASMANIA
VICTORIA
WESTERN AUSTRALIA
AUSTRALIAN CAPITAL TERRITORY
NORTHERN TERRITORY
15
What is Security of Payment legislation?
NEW SOUTH WALES
QUEENSLAND
SOUTH AUSTRALIA
TASMANIA
VICTORIA
WESTERN AUSTRALIA
AUSTRALIAN CAPITAL TERRITORY
NORTHERN TERRITORY
16
What is a principal contractor?
Appointment of a principal contractor
Failure to appoint a principal contractor
Responsibilities of principal contractors
Scenario 1
Scenario 2
Scenario 3
17
How is a contract terminated or rescinded?
Common law right of termination
Contractual right of termination
Statutory right of termination
Delay in termination
Consequences of termination
Rescission
Determination
18
Standard form contracts
Negotiation and mediation
Arbitration
Litigation
Expert determination
Dispute Resolution Boards
19
General damages and indemnities
Nature of damages for breach of contract
Calculation of damages for breach of contract
Indemnities
Warranties, representations and guarantees
Disclaimers and exclusion clauses
20
Claims outside the contract
Breach of statutory duty
Negligence
Claims under statute
Good faith obligations
Quantum meruit
21
What is proportionate liability?
When will proportionate liability apply?
The effect of proportionate liability on risk allocation
Contracting out of proportionate liability
How is apportionment of responsibility assessed?
Responses to proportionate liability
22
What is a green building?
Commonly used rating tools
Green Star
NABERS
IS Rating System
NatHERS
The legal framework
Relevance of the Building Code of Australia
Considerations in going green
23
What is design?
Who is responsible for design?
Warranties
Intellectual property rights in design
Design obligations and the duty to warn
24
What is ‘fitness for purpose’?
Express ‘fitness for purpose’ terms
‘Fitness for purpose’ terms implied by common law
‘Fitness for purpose’ terms implied by statute
‘Fitness for purpose’ terms in consultancy agreements
Industry standards, statutory regulations and their implications for ‘fitness for purpose’
Duty to warn of defects in design
Over what period does the ‘fitness for purpose’ term apply?
25
Introduction to PPSA
Understanding priority and extinguishment
Practical examples
Enforcing security interests
26
What is Digital Engineering and Building Information Modelling?
BIM in Australia
International approaches to BIM
Home
»
About Us
Glossary Term
Title
Description
×